New Handrails and Guards Inside an Ottawa Home: The Paid Steps

Too few Ottawa prices are published for interior handrails and guards to give you a range. What follows is what a quote pays for, step by step, with the Building Code rule behind each one. Handrails and guards are on neither City permit list, so ask the City rather than assume. Deck railings are outdoor work and are not covered on this site.

Price rangeToo few published prices to quote

Get quotes for this

Reviewed 2026-10-01 · why these pages have no ranges

Paid steps

Handrails and guards: what a quote pays for, in order

  1. Measuring heights and drops

    What it is
    Measuring the stair and every open edge the new rail or guard has to cover.
    On the bill because
    Required handrails sit 865 to 1 070 mm above a line drawn along the tread nosings. Guards go on open sides where the drop is more than 600 mm, and inside a dwelling unit they are at least 900 mm high.
    Ask for it itemized
    The heights the quote is built to, written on it.

    OBC 9.8.7.4.(1)-(2); 9.8.8.1.(1); 9.8.8.3.(2)

  2. Blocking and fastening

    What it is
    Solid wood in the wall behind each bracket.
    On the bill because
    In a single dwelling unit, a handrail fixed to wood studs or blocking is deemed to comply when the attachment points are not more than 1.2 m apart, the first one is within 300 mm of each end, and each point has at least 2 No. 8 wood screws reaching 32 mm into solid wood.
    Ask for it itemized
    Whether opening the wall for blocking, and closing it again, is in the price.

    OBC 9.8.7.7.(2)

  3. Removing the old railOlder homes

    What it is
    Taking off the old rail, balusters or guard.
    On the bill because
    Health Canada says a home built before 1960 probably contains lead-based paint, and warns against sanders, heat guns or blowlamps for removing it. Old painted balusters are worth testing before anyone cuts or strips them.
    Ask for it itemized
    Whether old painted parts are tested first, and who arranges it.

    Health Canada, Lead-based paint

  4. The handrail

    What it is
    The rail itself, its brackets and its ends.
    On the bill because
    A required handrail is continuously graspable from the bottom riser to the top riser. The clearance behind the handrail is at least 50 mm, or 60 mm where the surface behind it is rough or abrasive.
    Ask for it itemized
    The rail profile and species, priced apart from installation.

    OBC 9.8.7.2.(1); 9.8.7.5.(1)

  5. Guard infill

    What it is
    Balusters, panels or glass between the top of the guard and the floor or stair.
    On the bill because
    Openings stop a 100 mm sphere, and the triangle under a stair guard stops a 150 mm sphere. Nothing between 140 mm and 900 mm above the floor may make climbing easy, and glass in a guard is safety glass.
    Ask for it itemized
    The baluster count or panel type the price is for.

    OBC 9.8.8.5.(1)-(2); 9.8.8.6.(1); 9.8.8.7.(1)

  6. Finishing

    What it is
    Stain, paint or clear finish on the new parts.
    On the bill because
    Finishing takes its own time and material, separate from building the rail.
    Ask for it itemized
    Whether finishing is included, and who does it.

Totalon your written quote

Get quotes for this

City permit lists

Not listed: ask the City

Handrails and guards appear on neither the City's list of permit projects nor its list of exempt projects. Ask the City before work starts, especially if a guard is part of wider changes to a stair or floor opening.

On a designated heritage building or in a Heritage District Overlay, the City's permit exemptions do not apply: contact the City first.

No fee calculator on this page. Where a job does need a permit, this is how the City's fee is worked out.

Ask before you sign

  • Which side of the stair the handrail goes on, and why that side.
  • How the rail is fastened where no stud falls behind a bracket.
  • Whether the old balusters are reused or replaced.

The contract, cancellation, estimate and holdback rules that apply to every carpentry quote: before you sign any carpentry quote.

More on this work: Handrails & Guards

Quick answers

How many handrails does a stair inside my house need?

One, for a stair narrower than 1 100 mm inside a dwelling unit (Table 9.8.7.1.). Interior stairs with not more than 2 risers in a single dwelling unit need none (9.8.7.1.(3)(a)).

How high is the guard at the top of my stairs?

At least 900 mm inside a dwelling unit (9.8.8.3.(2)); on a stair it is measured to a line through the tread nosings (9.8.8.3.(4)). The handrail is a different part, at 865 to 1 070 mm.

Want this done at your place?

Tell us about your carpentry job and we'll send it to local Ottawa carpenters, who reply by email. We send it out to local contractors for you. Free, no pressure.

Fields marked are required.

We won't call you. There's no phone box above because we don't ask for one: your estimate comes by email, on your time.

Request received We’ve sent your details to local Ottawa carpenters. Interested carpenters reply by email. A confirmation is on its way to your inbox.
Find a Carpenter